Shell Mound boat ramp reopens as Levy County pauses dredging
The ramp, dock and parking area north of Cedar Key are open again while the county rethinks how to dredge the channel, and boaters are asked to watch water depths and tides.
The Shell Mound Boat Ramp north of Cedar Key is open again. The Levy County Board of County Commissioners said the ramp, dock and parking area reopened to the public after the county suspended a dredging project there.
In a press release issued Nov. 12, the county said it had paused dredging “to allow for further evaluation of the proposed dredging methodology and to determine the most effective approach for completing the project.” The ramp will stay open while that evaluation goes on.
What boaters should know
The county asked boaters to take care when using the ramp and to “remain mindful of existing water depths and tidal conditions.”
The release did not say when dredging will resume. The county said it will share further updates on the project as information becomes available.
A multi-year project
Shell Mound sits on County Road 326 inside the county-owned Shell Mound Campground, within the Lower Suwannee National Wildlife Refuge and next to the Cedar Key Scrub State Reserve. It is one of nine public boat ramps in Levy County, and it lets campers launch straight from the campground into Suwannee Sound.
The dredging is one phase of a longer effort to improve the site, funded in part through the Florida Fish and Wildlife Conservation Commission’s Florida Boating Improvement Program. In a grant application dated March 26, Levy County Parks and Recreation Director Matt Weldon wrote that the county received program funding in 2021 to design and permit the dredging, and in 2024 to carry it out. At the time, the county expected the dredging to be finished in 2026.
The same application asked for $195,000 for the next phase: engineering, design and permits to replace the deteriorated concrete ramp and its retaining wall, replace the aging fixed dock, add a second fixed dock for more tie-up space, and stabilize the shoreline. The county planned design and permitting between August 2026 and March 2027, with construction from August to December 2027 if it wins further grant money.
The county said in the application that better boating access should bring more campers to Shell Mound, and that the extra camping fees would help pay for planned upgrades to the campground’s sewer and electrical systems.
Who to call
Questions about the ramp can go to Levy County Parks and Recreation at 352-486-5127, or to the Board of County Commissioners at 352-486-5218 or LevyBoCC@LevyCounty.org.